ASTM E2026 defines investigation levels by how much data is collected and how deeply the building is analyzed. Here is what each of our levels includes and when we recommend it.

Level 0Level 1Level 2
TypeRecords-based desktop assessmentSRA with field assessmentDetailed engineering assessment
Site visitNoYes — Qualified Field AssessorYes — plus construction document review
Analysis, review, stampPEPEPE
OutputsHazard data, SEL and SULLevel 0 + field observations, building stabilityLevel 1 + ASCE 41 Tier 1/2 or FEMA P-58, building-specific fragility, retrofit scoping
Turnaround3 business days from complete data5 business days after the site visitQuoted per project
Typical useOwner due diligence, portfolio pre-screeningAgency, CMBS, life-company, and HUD/FHA submissionsHigh-value or complex assets, retrofit decisions

Level 0 — desktop assessment

A records-based assessment using published hazard data (USGS PGA at 10% in 50 years, spectral values, site class), fault distances, liquefaction and landslide mapping, and the building's type and age. We calculate SEL and SUL, and the PE reviews and stamps the report. There is no site visit.

Level 1 — SRA with field assessment

Everything in Level 0, plus a site visit by a Qualified Field Assessor to observe the structural system, critical connections, and site conditions. Our team completes the analysis, and the PE reviews and stamps the report. Fannie Mae requires a Level 1 SRA for properties with a Structural Risk Factor (Form 4099.C) — see Fannie Mae seismic requirements.

Level 2 — detailed engineering assessment

Everything in Level 1, plus review of structural drawings and calculations and building-specific analysis (ASCE 41 Tier 1 / Tier 2 or FEMA P-58), with retrofit scoping and cost-range estimates. Used when a Level 1 result needs refinement or a retrofit decision is on the table. For how lenders treat the result, see the 20% and 40% SEL lines explained.

Turnaround

Inquiry responseSame business day (Mon–Fri)
Level 0 desktop assessment3 business days from complete data
Level 1 SRAPE-reviewed and stamped report 5 business days after the site visit
Level 2 detailed assessmentQuoted per project

Not sure which level your lender needs? Send us the scope letter — the required level is usually stated there. See also ASTM E2557 vs. E2026.